Security for expenses in party wall matters (section 12)

When an adjoining owner can ask for security, how much is reasonable, and how the money is held and released.

Security for expenses is money the building owner sets aside, under section 12 of the Party Wall etc. Act 1996, so that the adjoining owner is protected if the notified work is left unfinished or causes loss. The adjoining owner can ask for it before the work starts; if the owners cannot agree an amount, the party wall surveyors decide it in the award. It is most often requested for basements, underpinning and other high-risk work.

Key points

  • The adjoining owner must request security before the notified work starts [1][2].
  • The amount is agreed or, failing agreement, determined by the surveyors under section 10.
  • Security is usually held in a stakeholder or escrow account under terms set out in the award.
  • It protects against unfinished work; damage is compensated separately under section 7.

When is security for expenses requested?

ProjectWhy security is often requested
Basement excavation and underpinningLong, complex works near the neighbour's foundations
Demolition and rebuilding of a party wallThe neighbour's home is exposed if the job stops
Large rear or side extensions with deep excavationSection 6 risk to the neighbour's structure
Developer or company building ownerConcern about insolvency or a sale mid-project

See our basement excavation guide for the notices that usually come with these projects.

How much security is reasonable?

There is no formula in the Act. Surveyors usually estimate the cost of making the neighbour's property safe and weathertight if the works stopped at the worst moment, and sometimes the cost of reinstatement. The building owner can challenge an excessive figure through their surveyor. Keep it proportionate: security that is far larger than the realistic exposure ties up project cash.

How the money is held and released

  • The award should name the account (often a solicitor's client account or an escrow service) and who controls it.
  • It should say when the money is released: usually after completion and a final inspection, or in stages.
  • Interest, fees for the account and the process for a claim should be written down.
  • If the building owner sells, the award should say what happens to the security.

Can the building owner ask for security too?

Yes, in limited cases: where the adjoining owner asks for additional work for their own benefit, the building owner can ask for security for the adjoining owner's share of the cost. Your surveyor will advise whether it applies.

Plan the party wall side of your project: check the notice type, the dates you need to hit and a realistic fee budget before you instruct a surveyor.

Basement excavation and party walls · Check which notice applies · Plan the notice timeline · Estimate surveyor fees · Request surveyor quotes

How an adjoining owner requests security

  1. Reply to the notice (consent or dissent) and, before work starts, ask in writing for security under section 12.
  2. Give your surveyor the reasons: depth of excavation, condition of your building, the building owner's circumstances.
  3. Owners try to agree an amount and how it is held; if they cannot, the surveyors determine it in the award.
  4. Work should not start until security required by the award has been provided.

Building owners: keeping security proportionate

  • Share the engineer's method statement and temporary works design early: risk you can explain is risk surveyors can price lower.
  • Offer staged release linked to milestones such as completion of underpinning.
  • Show your contractor's insurance, which is separate from security but reassures neighbours.
  • Agree the account and release terms in the award so money is not held indefinitely.

Frequently asked questions

What is security for expenses in a party wall award?

A sum the building owner sets aside, at the adjoining owner's request under section 12, to cover the risk of the notified work being left unfinished or causing loss.

Who decides the amount of security for expenses?

The owners can agree it; otherwise the party wall surveyors determine it in the award.

When should security for expenses be requested?

Before the notified work starts. It is common for basements, underpinning and party wall rebuilding.

Is security for expenses the same as compensation for damage?

No. Damage caused by the works is compensated under section 7; security covers the risk that the work is not completed properly.