Neighbour ignoring your party wall notice? The 14-day and 10-day timeline step by step

Neighbour ignoring your party wall notice? The 14-day deemed dissent rule, the 10-day request, s.10(4) appointment and what to do while you wait.

If your neighbour says nothing for 14 days after a party structure notice is served, the law treats them as having dissented, and a dispute is deemed to have arisen. You then ask them in writing to appoint a surveyor. If they still do nothing for 10 days, you can appoint a surveyor on their behalf under section 10(4) of the Party Wall etc. Act 1996. Silence doesn't block your project. It moves it onto the surveyor route, which takes time, so plan for it now.

Key takeaways

  • Day 14: no written consent means deemed dissent (s.5 for party structure notices, s.6(7) for excavation notices).
  • Then: send a written request asking your neighbour to appoint a surveyor. They have 10 days (s.10(4)).
  • Still nothing: you appoint a surveyor on their behalf. You cannot act as your own surveyor, and you cannot pick yourself for them.
  • You normally pay the reasonable fees of both surveyors.
  • Don't start notifiable work until you have written consent or an award, and the notice period has run.

My neighbour hasn't replied to the party wall notice: what does the law say?

The Party Wall etc. Act 1996 (England and Wales) has a built-in answer to silence. For a party structure notice, section 5 says that an owner who "does not serve a notice indicating his consent to it within the period of fourteen days" is "deemed to have dissented", and "a dispute shall be deemed to have arisen" [1]. Section 6(7) uses the same mechanism for adjacent excavation notices, the 3 m and 6 m rules [2]. For a new wall on the boundary line (section 1), the rules on silence work a little differently, so ask your surveyor how they apply to your notice.

"Deemed dissent" is the phrase you'll see. It doesn't mean your neighbour objects. As one forum reply put it: "No response means that you automatically 'dissent' after 14-days of service" [3]. In practice, a missing signature is a procedural step, not a dead end.

The 14-day and 10-day timeline, step by step

Step When What happens Legal basis
1. Serve the notice Day 0 Notice served by a method you can prove: tracked post or witnessed hand delivery [4] s.1, s.3 or s.6
2. Wait for a reply Days 1–14 Neighbour can consent, dissent and name a surveyor, or agree to an agreed surveyor s.5, s.6(7) [1][2]
3. Deemed dissent End of day 14 No written consent = dispute deemed to have arisen s.5, s.6(7) [1][2]
4. Request to appoint Straight after day 14 You write asking them to appoint a surveyor within 10 days s.10(4) [5]
5. Appointment on their behalf After 10 more days If they refuse or neglect, "the other party may make the appointment on his behalf" s.10(4) [5]
6. Third surveyor selected Early on Your surveyor and the appointed surveyor select a third surveyor (used only if they disagree) s.10(1)(b) [5]
7. Condition survey and award Usually weeks Surveyors record your neighbour's property and agree the award s.10 [5][6]
8. Appeal window 14 days from service of the award Either side may appeal to the county court s.10(17) [5]

On top of this, the notice period still applies. You must give at least two months for work to an existing party wall and one month for a new boundary wall or excavation [7]. The surveyor route often runs alongside that period, so a well-timed notice loses little or no time. A late one can lose weeks.

How long does the award stage take? There is no official timescale. HomeOwners Alliance notes that guidance gives no overall timescale for resolving a dispute [8]. One London owner reported the award took about 10 weeks [9]. Another felt "it took longer than planning permission" [10].

Should I send a second notice or knock on their door?

Both are reasonable, as long as your formal steps stay in writing. HomeOwners Alliance's FAQ advises: "you need to issue another, and they have 10 more days to respond" [8]. That "another" letter is the section 10(4) request in the table above.

A friendly knock often helps. One owner whose HMO landlord neighbour had been silent since January asked: "Would I be unreasonable to knock on his door one evening with a copy?" [11]. Meanwhile their loft was due to start in May, and the builder's quote had already gone up by £4k [11]. A conversation can't replace the paperwork, but it can save weeks.

Your 10-day request letter should:

  • [ ] Refer to the original notice and its date of service.
  • [ ] State that 14 days have passed without written consent, so a dispute is deemed to have arisen.
  • [ ] Ask them to appoint a surveyor within 10 days, or to agree to an agreed surveyor (you can name one and attach a fixed-fee quote).
  • [ ] Explain that if they don't, you may appoint a surveyor on their behalf under s.10(4).
  • [ ] Remind them that you, as building owner, normally pay the reasonable surveyor fees [6].
  • [ ] Be served the same provable way as the notice, with copies kept.

Check the address first. If the neighbour is a landlord or the property is let, the owner may not live there. Land Registry may show a company or "rental agency" as owner [12]. Notices sent only to tenants can create avoidable delay.

Who can I appoint on my neighbour's behalf?

You choose a surveyor to act for the adjoining owner, but that person doesn't act for you. GOV.UK confirms you can appoint a surveyor on your neighbour's behalf if they refuse or fail to do so, and that "You cannot act as your own surveyor" [6]. RICS adds that a surveyor appointed under the Act "is under a duty to act impartially regardless of who appointed them" [13].

Good practice when choosing:

  • Pick someone independent of your architect, engineer and builder.
  • Prefer a local surveyor. One neighbour's surveyor was "190 MILES AWAY!", which added travel costs [14].
  • Get a written quote with the hourly rate, expected hours and disbursements. See our party wall surveyor fees in London guide for the figures owners report (roughly £700–£1,400 + VAT per surveyor in forum examples).

If the surveyor appointed for your neighbour then fails to act for 10 days after a request, section 10(7) allows your surveyor to proceed alone ("ex parte") on that point [5]. The Act has a fallback for each stage where someone stalls.

Can I start building while I wait?

Not the notifiable work. RICS says: "You must have an Award before you can start work under the Act" unless your neighbour agrees in writing [13]. HomeOwners Alliance is equally blunt: "Do not carry on with building work if your neighbour refuses a party wall agreement" [8]. Starting early risks an injunction and expensive disputes. Our loft and rear extension guide covers what skipping the process can cost.

What you can do while you wait:

  1. Keep your evidence. Proof of posting, delivery receipts, photos of hand delivery, and copies of every letter.
  2. Brief your builder. Agree a realistic start date and ask whether any work that doesn't touch the party wall or come within the excavation zones can be sequenced first. Confirm with your surveyor that it really falls outside the notice.
  3. Send complete drawings to the surveyors early. Missing information means more hours and more fees.
  4. Watch the clock on your notice. A notice is valid for one year if work hasn't started [7]. Don't let a slow dispute push you past it.
  5. Map the timeline. Our free timeline planner helps you see where the 14 days, 10 days, notice period and award fall against your build date.

Decision tree: what do I do on day 15?

  • Neighbour consented in writing? → No surveyor needed. Offer a condition survey anyway and keep it on file.
  • Neighbour dissented and named a surveyor? → Instruct yours. The two select a third.
  • Neighbour agreed to an agreed surveyor? → One surveyor prepares the award. This is usually the cheapest route. See our guide on agreed surveyor vs two surveyors.
  • Silence? → Send the s.10(4) request. After 10 days, appoint a surveyor on their behalf.

FAQ

What happens if my neighbour ignores a party wall notice? After 14 days without written consent, they are deemed to have dissented and a dispute exists [1]. You then ask them to appoint a surveyor. If they don't within 10 days, you can appoint one for them [5].

Does an unsigned party wall agreement mean I can't build? No, it means you go down the surveyor route. You need an award before starting notifiable work, unless they consent in writing [13].

Can I appoint my own surveyor to act for my neighbour too? Only if your neighbour agrees to an agreed surveyor. If they're silent, s.10(4) lets you appoint a separate surveyor on their behalf [5]. You can never be the surveyor yourself [6].

Who pays for the surveyor I appoint for my neighbour? The surveyors decide in the award who pays reasonable costs, and that is normally the building owner [5][13].

How long will the party wall process take if my neighbour doesn't respond? At least 14 + 10 days before the second surveyor is appointed, plus the time to agree the award. One owner reported about 10 weeks [9]. The notice period of one or two months applies as well.

Get the surveyor side moving

Check which notice applies with our free notice checker. Then compare providers and request quotes from party wall surveyors covering Camden, Islington, Hackney, Wandsworth and Kensington & Chelsea through our enquiry form. We're an independent directory and can't guarantee a match.

Related reading: Neighbour started work without a party wall notice · Received a party wall notice? A calm guide for neighbours · Party wall notice periods

This is not legal advice. This article gives general information about the Party Wall etc. Act 1996 in England and Wales. Deadlines run from the date of service and are strict. Consult a qualified party wall surveyor or a solicitor about your notice before relying on any of the steps above.

Sources

  1. Party Wall etc. Act 1996, section 5 (legislation.gov.uk)
  2. Party Wall etc. Act 1996, section 6 (legislation.gov.uk)
  3. Singletrack World – Party wall act help
  4. BuildHub – Neighbour never around to sign party wall agreement
  5. Party Wall etc. Act 1996, section 10 (legislation.gov.uk)
  6. GOV.UK – Party walls and building work: if you cannot agree
  7. ARAG – Party Wall Act explained (law guide, 06/2025)
  8. HomeOwners Alliance – Can a neighbour refuse a party wall agreement?
  9. Mumsnet – Party wall hell, help
  10. MoneySavingExpert forum – Party wall act: extortionate fees and ruins relations with neighbours
  11. Mumsnet – Neighbour ignoring Party Wall agreement docs
  12. MoneySavingExpert forum – Party wall notice not served
  13. RICS – Party walls guide (2020)
  14. Mumsnet – Party wall surveyor fees: disbursements

General information about the Party Wall etc. Act 1996 in England and Wales, not legal advice. Notices, awards and fees depend on your works and your neighbours; confirm with a party wall surveyor or solicitor before you serve notice or start work.