Removing a chimney breast from a party wall needs a section 2 party wall notice at least two months before work starts, building regulations approval for the structural support, and usually a structural engineer's design. less.co.uk's October 2026 guide puts removal at about £1,500–£3,000 for one floor, £2,500–£5,000 for two floors and £3,000–£6,000 to remove the breast and stack, plus £300–£600 for an engineer and £250–£400 for building control.
Key points
- Section 2 of the Act covers cutting away projections such as chimney breasts from a party wall; the notice period is two months [1].
- The remaining chimney above must be supported: gallows brackets only meet building regulations in set conditions; otherwise a steel beam is designed [2].
- Check whether the neighbour's flue or breast shares the stack, and what happens to the stack if yours goes.
- A schedule of condition of the neighbour's side protects both of you.
Chimney breast removal cost (2026)
| Item | Typical | Range |
|---|---|---|
| Breast removal, one floor | £2,250 | £1,500–£3,000 |
| Breast removal, two floors (with support steelwork) | £3,750 | £2,500–£5,000 |
| Full removal: breast and stack | £4,500 | £3,000–£6,000 |
| Structural engineer report | – | £300–£600 |
| Building control fee | – | £250–£400 |
| Party wall surveyor, per neighbour | – | £700–£1,500 |
The party wall notice
Serve a party structure notice under section 2 on every adjoining owner of the wall, including leaseholders with more than a year left on their lease. Describe the work, attach the engineer's drawing, and give a start date at least two months later. Your neighbour can consent, dissent and appoint a surveyor, or ask for an agreed surveyor. Draft it with our notice templates.
Building regulations and structural support
Removing all or part of a chimney breast is structural work. Council building control guidance is clear that removing part or all of a chimney requires building regulations approval; gallows brackets are only allowed under set conditions (for example a sound party wall at least 215 mm thick and no more than two storeys), otherwise an engineer-designed steel beam is needed [2]. Your engineer will specify how: a steel beam bearing on padstones, or proprietary brackets where building control accepts them. Fire safety also matters: any opening in the party wall must keep its fire separation.
What can go wrong
- Cracking or debris on the neighbour's side, especially in older lime-mortar walls.
- Soot and dust entering the neighbour's flue or fireplace.
- An unsupported stack left behind in the loft.
- A future buyer's surveyor asking for building control completion and the party wall award: keep both.
Step by step
- Engineer designs support; building control application submitted.
- Section 2 notice served on the neighbour with drawings, two months before the start.
- Consent, or surveyors appointed and an award made after a schedule of condition.
- Support installed, breast removed, opening made good and fire-stopped.
- Building control sign-off; final party wall inspection.
Plan the party wall side of your project: check the notice type, the dates you need to hit and a realistic fee budget before you instruct a surveyor.
Check which notice applies · Plan the notice timeline · Estimate surveyor fees · Request surveyor quotes
Flats and terraces: whose chimney is it?
In a terrace, the chimney breast usually projects from the party wall and the stack is often shared with the neighbour's flues. In converted flats, the breast on the floor above may belong to a different flat: removing yours at ground level without support affects that owner, who is also an adjoining owner entitled to notice. Check the title plans and lease, and serve notices on every owner whose property the work affects.
Questions to ask your builder and engineer
- Which support method are you designing, and has building control accepted it?
- Is the neighbour's flue still in use, and how will it be protected from debris and soot?
- Will any part of the stack or breast above remain, and how is it carried?
- How will the opening in the party wall be fire-stopped and made good?
- Who will serve the party wall notice, and does the programme allow two months?
Frequently asked questions
Do I need a party wall agreement to remove a chimney breast?
Yes, if the breast is on a party wall: it is section 2 work needing two months' notice, followed by consent or a party wall award.
How much does it cost to remove a chimney breast?
About £1,500–£3,000 for one floor and £2,500–£5,000 for two floors, according to less.co.uk (October 2026), plus engineer, building control and party wall fees.
Do I need building regulations to remove a chimney breast?
Yes. It is structural work, and building control must approve how the chimney above is supported.
Can I remove the chimney breast but keep the stack?
Often, if the stack is properly supported, but your engineer and building control must approve the support.