Party Wall etc. Act 1996 · England and Wales

Do I need a party wall notice?

Pick your project to see which notices the Act requires, run the 3 m / 6 m excavation test with your own measurements, and get the latest date to serve each notice.

2. Will you build a wall on or up to the boundary line?
3. Will you cut into, raise or underpin the existing party wall?
4. Excavation (the 3 m / 6 m rule)
We show the latest date to serve each notice.

The 3 metre and 6 metre rules

An excavation needs a section 6 notice if it is within 3 metres of any part of a neighbour's building or structure and goes deeper than their foundations, or within 6 metres and meets a line drawn down at 45 degrees from the bottom of their foundations, in the direction of your dig. Measure from the neighbour's building, not the boundary.

Neighbourtheir foundations45° line3 m6 mnotifiable: within 3 m, deepernotifiable: within 6 m,below the 45° line

Which notice for which project

ProjectNoticesWhy
Loft conversion with steel beams into the party walls2Cutting into a party wall to take the bearing of a beam is section 2 work.
Rear extension (new foundations near the neighbour)s6 if within 3 m / 6 m and deep enough, s1 if on the boundaryFoundations usually trigger section 6 if they are close and deep enough; a wall built on or up to the boundary line adds section 1.
Side return or wrap-around extensions1 if on the boundary, s2 if you work on the party wall, s6 if within 3 m / 6 m and deep enoughOften all three: a wall on the boundary (s1), work to the existing party wall (s2) and foundations near the neighbour (s6).
Basement or cellar excavations2, s6 if within 3 m / 6 m and deep enoughExtending a party wall downwards is section 2 work; digging near the neighbour usually adds section 6.
Removing a chimney breast on a party walls2Cutting away projections from a party wall is section 2 work.
Inserting a damp-proof course in the party walls2Listed by the government booklet as section 2 work.
Underpinning the party walls2, s6 if within 3 m / 6 m and deep enoughUnderpinning the whole thickness of a party wall is section 2 work.
Raising the party wall (adding a storey)s2Raising the height of a party wall is section 2 work.
Demolishing and rebuilding a party walls2Section 2 work.
New wall on the boundary line (house or garden wall)s1Section 1 line of junction notice. A wall astride the line needs the neighbour's written consent.
Shelves, kitchen units, rewiring sockets or replasteringUsually noneThe booklet says notice is generally not necessary for drilling for plugs and screws, recessed wiring and sockets, or replastering.

Notice periods at a glance

  • Party structure notice (section 2): at least 2 months before work to the party wall.
  • Line of junction notice (section 1): at least 1 month before building the wall.
  • Adjacent excavation notice (section 6): at least 1 month before digging, with drawings.
  • Your neighbour has 14 days to respond. If they do nothing, a dispute is deemed to have arisen and surveyors are appointed.
  • A notice is only valid for a year, so don't serve it too early.

Source

Party Wall etc. Act 1996, sections 1, 2 and 6, as explained in the government's Party Wall etc. Act 1996: explanatory booklet, read on 13 November 2026. The Act applies in England and Wales. A party wall surveyor should confirm which notices apply to your drawings.

General information, not legal advice. Nothing you enter here is sent to us.