Party wall damage: how to claim compensation

Your rights under sections 7 and 11, the evidence that wins claims, and what to do if no notice was served.

If notified party wall work damages your property, the building owner must compensate you for the loss or damage (section 7(2) of the Party Wall etc. Act 1996), and you can choose to be paid the cost of repairs instead of having the builder make good (section 11(8)). The schedule of condition recorded before work started is the key evidence, and the party wall surveyors settle disputes about the cause and the amount.

Key points

  • Report damage in writing as soon as you notice it, with dated photos.
  • Compare it with the schedule of condition taken before the works.
  • Where surveyors were appointed, they deal with the claim under the award; an agreed surveyor acts for both sides.
  • If no notice was served, the Act's procedure may not apply and you may need a claim in nuisance or negligence.

What to do if your neighbour's works damage your home

  1. Photograph and measure cracks, stains or movement, with a date and a reference (a coin or ruler).
  2. Write to the building owner and the surveyors, describing the damage and when it appeared.
  3. Ask the surveyors to inspect and compare it with the schedule of condition.
  4. Agree whether the builder will make good or whether you will be paid the cost (your choice under section 11(8)).
  5. If the parties cannot agree, the surveyors make an addendum award; it can be appealed to the county court within 14 days.

Typical party wall damage

DamageUsual causeEvidence that helps
New cracks in plaster on the shared wallVibration, cutting in steels, chimney breast removalSchedule of condition photos of the same wall
Cracks at the rear cornerExcavation for an extension (section 6)Crack monitoring before and during the dig
Water ingressFlashings, gutters or roofs disturbedDates of rain and of the roof works
Damaged decorations or fittingsDrilling, debris through fluesPhotos of rooms before works

Damage when no party wall notice was served

If your neighbour did notifiable work without a notice, you are not limited to the Act's procedure. You can ask for work to stop until notices are served, and you may have a claim in nuisance or negligence. Read what to do if a neighbour started work without a party wall notice.

Who pays the surveyors' fees for a damage claim?

Under the award, the building owner normally pays the surveyors' reasonable fees, including dealing with damage caused by the works. Fees for disputes that are unfounded can be awarded differently; the surveyors decide. See how to challenge party wall surveyor fees.

Plan the party wall side of your project: check the notice type, the dates you need to hit and a realistic fee budget before you instruct a surveyor.

Read the schedule of condition guide · Check which notice applies · Plan the notice timeline · Estimate surveyor fees · Request surveyor quotes

Evidence checklist

  • The schedule of condition (photos and notes) and any crack monitoring records.
  • Dated photos and videos of the damage, with a scale reference.
  • A diary of works: dates of excavation, cutting in steels, vibration or heavy plant.
  • Correspondence with the builder, the building owner and the surveyors.
  • Repair quotes if you are asking for payment instead of making good.

Appeals, insurance and time limits

A party wall award, including an addendum award about damage, can be appealed to the county court within 14 days of service. Check your own home insurance too: it may cover sudden damage, but insurers will look to the building owner, whose contractor should carry public liability insurance. Report damage promptly; the longer you wait, the harder it is to link it to the works.

Frequently asked questions

Who pays if party wall works damage my house?

The building owner. Section 7(2) of the Act requires them to compensate adjoining owners and occupiers for loss or damage caused by the notified works.

Can I choose money instead of repairs?

Yes. Under section 11(8) the adjoining owner can require the cost of making good to be determined and paid instead of the builder doing the repairs.

How long do I have to claim for party wall damage?

Report it promptly. The award usually sets a final inspection; later claims are harder to prove, though normal limitation periods apply.

What if there is no schedule of condition?

You can still claim, but it is harder to show the damage is new. Photos, estate agent images and witnesses help.